“Box-in-box” method for renewal of modular joints

Principle

The mageba “box-in-box” method enables modular expansion joints to be replaced without any impact on the bridge’s structure. The substructure of the existing expansion joint is left in place, and a new joint is installed on top of it, with the support bar boxes of the new joint designed to fit into those of the existing one.

Applications

The “box-in-box” method is especially suitable when modular expansion joints are to be replaced with minimum impact on the bridge structure and in the quickest possible time.

PROSPECT-box-in-box-ch-enPROSPECT-box-in-box-ch-en

Image gallery

  • Kasten-in-Kasten-img1

    Old 3-gap expansion joint after removal of asphalt and waterproofing membrane at each side

  • Kasten-in-Kasten-img2

    Cutting to enable the support bars of the old joint to be lifted out

  • Kasten-in-Kasten-img3

    Substructure after cleaning

  • Kasten-in-Kasten-img4

    New expansion joint during installation, after connection to the structure

  • Kasten-in-Kasten-img5

    Renewal of a 2-gap modular joint almost completed

  • Kasten-in-Kasten-img6

    Traffic management during renewal of a joint in phases