Fits like a glove

Back

31.01.2018

Verrazano-Bridge-mainimg

Newsflash-Verrazano-Narrows-Bridge-3D-sliding-finger-joint

3D representation of a new sliding finger joint for movements of 2,700 mm

Newsflash-Verrazano-Narrows-Bridge-inspection-expansion-joint

Inspection of one of the largest sliding finger joints (movement capacity 2,700 mm) prior to renovation

Newsflash-Verrazano-Narrows-Bridge-sliding-finger-joint-trial-assembly

Trial assembly of a sliding finger joint (movement capacity 2,700 mm) in a mageba factory prior to delivery to site

Newsflash-Verrazano-Narrows-Bridge-sliding-finger-joint-trial-assembly-2

Trial assembly of one of the sliding finger joints (movement capacity 2,000 mm) in a mageba factory prior to delivery to site

Newsflash-Verrazano-Narrows-Bridge-Removal-Old-Fingers-substructure

Step 1 on site: Removal of old sliding finger joint (movement capacity 2,000 mm)

Newsflash-Verrazano-Narrows-Bridge-Installed-new-substruture

Step 2 on site: Installation of new substructure of expansion joint (movement capacity 2,000 mm)

Newsflash-Verrazano-Narrows-Bridge-substructure-installed-refurbished-plates

Step 3 on site: Installation of sliding finger plates on the new substructure (movement capacity 2,000 mm)

Newsflash-Verrazano-Narrows-Bridge-joint-installed

Fully installed sliding finger joint (movement capacity 2,000 mm)

Newsflash-Verrazano-Narrows-Bridge-sliding-finger-joint

Fully installed sliding finger joint (movement capacity 2,700 mm)

Newsflash-Verrazano-Narrows-Bridge-scope

Locations of the bridge’s upper deck expansion joints and their movement capacities.

Newsflash-Verrazano-Narrows-Bridge-sliding-finger-expansion-joints

The double-decked bridge was built with enormous sliding finger expansion joints in both its upper and lower decks, which need to be replaced or substantially renewed

Verrazano-Bridge-3D-finger-img2

3D representation of a new sliding finger joint for movements of 2,000 mm